Saturday, September 20, 2008

16-09-2007 To 16-09-2008 (Had Been A Year)

Hello guys... 16/09/2007, since like just yesterday. The time moves so fast nowadays. This year 16/09/2008, had been a year that my grand father had past away. We had some family gathering at uncle ed place. Some BBQ dinner. This time I'm not the early bird already, because i had to wait for my daughter to be ready. Went to uncle Ed place around 7pm. Below are some of the picture that i had took that night.


Chicken Wings


More Chicken Wings


The Cook Of The Night


Auntie's And Uncle's


The One In Blue Is Mummy

Monday, September 15, 2008

Princess Ethana Lim (4 Months Old)

Hello everyone. I'm 4 months old now. Below are some of my picture that had taken by my mummy. Guess what, my mummy makes me laugh and make me post in many direction.


I look so so sad... because is the camera again..... hehehe


My mum make me laugh again......


Don't I look cute here......


Hello i can see you there......

Yes, what can i do for you there.....

Cleaning The Rotor At HQ

Updated of the generator overhaul. You can see the below picture show how clean is the rotor after 4 days of cleaning at our workshop. And the red coating is to test is there any crack on the end cap of the rotor. And at the end of the testing we didn't find any crack and we can said the rotor is still in good condition.


After cleaning the rotor with paint remover. And now its look super clean....

Test is there any crack on the End Cap

And now I'm not in the generator overhaul. I'm back in maintenance section. But that ten days of working under the sun is super hot....... and i had loss 2kg for that hard work.

Friday, September 5, 2008

Generator Overhaul At Jerudong Power Station (JPS1)

Hello Guys, sorry for the last updated. Was busy starting 01/09/2008 at the generator overhaul at Jerudong Power Station. This is my 1st time that been assign to the generator overhaul. Today is days 5 for the overhauling. The first day was ok, but the days go by.... is really very very tired. And I was told that the overhaul for the 1st generator will be 23 days to complete the job. Which is pull the rotor out and put the rotor in after all the testing that will be done by the BRUSH guys that come from UK. There are ALI & MICK. Just before puting in the rotor me and my partner Raymond must clean everything off. The rotor was the most hard part to pull it out from the stator winding. Everything must be measure and calculate. Below there are some pictures that show how big is the rotor and the stator winding.....

We usually see the motor in a small size. And inside the D.C motor are rotor and stator. Everything is small in size....... Just had a look how BIG is the rotor and stator.



Rotor (Center) and the Stator Winding (Around the rotor).


See how dirty is the rotor and the Fan Rod.


The other half of the cover had been taken out( Weight about 2 tons).


The rotor is fully out from the stator winding. And see again how dirty is the rotor. And its weight around 10 tons.

So the rotor is out and the next job will be testing and CLEANING up all the black oil thing u see there.

And its 18 days to due dates for us.